Analysis

What is changing in energy for data centres and large industry in Spain

We follow the grid, regulation and the electricity market because they decide whether a project can connect, comply and be financed. Here we summarise the data, our models and the technical criteria we apply.

18.5 GWof transmission-grid access granted to new demand
0 MWof data centres in service out of 6.3 GW granted
397 hof negative wholesale prices in Q1 2026
85 %of charges recoverable by electro-intensive consumers

Public data from Red Eléctrica, OMIE, MITECO and the Ministry of Industry, October 2026.

Grid access

The grid is no longer a formality. It is the scarce resource

Transmission-grid access granted to new demand adds up to about 18.5 GW. Data centres hold the largest share, about 6.3 GW, but none of it is in service yet, and the sector's requests exceed 22 GW. Industry faces the same question: how to grow with the power it already has under contract.

Our approach: before asking for more grid, measure how the existing connection is used. Storage and EMS can create headroom within the capacity already available.

02 0004 0006 0008 000Data centres6 329 MWIndustry5 838 MWOther demand6 354 MWMWIn serviceGranted, not yet in service
Transmission-grid access granted to demand, October 2026
Illustration: rack aisle in a data-centre hall
Illustration: rack aisle in a data-centre hall

Regulation

Spain's data-centre decree: renewable power, hour by hour

The Government has softened the August draft and sent a revised text to the Council of State. The core principle stays: consumption will have to be covered by renewable generation matched hour by hour.

TopicDraft, August 2026Revised text, October 2026Technical reading
ScopeGrid access of 1 MW or moreGrid access of 10 MW or more; reporting duty from 500 kW ITMore sites affected than expected; metering and reporting from day one
Hourly renewable matching80 % from the startOptional transition of up to 5 years: 60 % in P1 until 2028, then 70 % in P1 and 60 % in P2; requires joining the automatic power-reduction schemeStorage and EMS are needed to carry solar energy into the evening and night and to manage reductions
Age of linked renewablesUp to 18 monthsUp to 36 months; no limit for PV without a prior PPAMore plants and PPAs available; minimum PPA term down from 10 to 6 years
EfficiencyPUE ≤ 1.15 and WUE ≤ 0.1PUE ≤ 1.25 as a transitional ceiling; top EU water classCooling design and EMS control become part of compliance

Status at the time of writing: text at the Council of State, not yet final.

Solar-Tec model

How much battery it takes to reach 80 % hour by hour

Illustrative model: a 10 MW IT data centre (12.5 MW with PUE 1.25) and 60 MWp of PV on a sunny day. PV alone covers roughly half of the hours; the battery moves the midday surplus into the evening and night.

0510152025303500:0006:0012:0018:0024:00MWPV, directBatteryGridPV output
Hourly supply of a 10 MW IT data centre with 60 MWp PV and a 20 MW / 120 MWh BESS
Battery added to 60 MWp PVLoad matched hour by hour (sunny day)
No battery47 %
20 MW / 60 MWh66 %
20 MW / 90 MWh75 %
20 MW / 120 MWh85 %
20 MW / 150 MWh89 %

Audit note: a sunny day is the best case. Annual compliance is checked with all 8,760 hourly values, winter weeks, battery degradation and a mix of solar and wind.

Market

Midday gets cheaper. The evening does not

In the first quarter of 2026 Spain recorded 397 hours with negative wholesale prices, against 48 in the same quarter of 2025.

Storage that charges at midday and discharges in the evening captures that spread and, at the same time, helps meet hourly matching.

Large consumers

Peak shaving: pay only for the power you really need

Illustrative model of an industrial plant with production peaks above 8 MW. A 2 MW / 4 MWh battery keeps demand below 6.5 MW, so contracted power and excess-power charges can be reduced.

0246810Target maximum demand 6.5 MW00:0006:0012:0018:0024:00MWSupplied by the gridPeak covered by the battery
Industrial load profile with battery peak shaving
Maximum demand
8.5 MW → 6.5 MW (−24 %)
Energy shifted
3.9 MWh per day
Battery
2 MW / 4 MWh, one cycle per day

Audit criteria

What we measure in an energy study

IndicatorReferenceWhy it matters
Power factor (cos φ)Reactive energy is charged below 0.95Direct cost on the bill; correction usually pays back quickly
Voltage harmonic distortion (THD)EN 50160: up to 8 % at the supply pointOverheating of transformers and cables, nuisance trips
Current harmonics from drives, rectifiers and UPSIEC 61000 / IEEE 519 guidanceDefines filters and the PCS specification
Voltage sags and interruptionsCounted and classified per EN 50160Lost production; ride-through requirement for storage
Maximum demand per tariff periodContracted power P1 to P6 vs measured peaksContract optimisation and peak-shaving potential
Load factor and peak-to-average ratioMeasured on 15-minute dataBattery sizing and business case
PUE (data centres)Transitional ceiling of 1.25 in the revised textCooling and EMS strategy

Electro-intensive industry

Support that depends on good data

Consumers certified as electro-intensive can recover up to 85 % of the renewable and cogeneration support charges they pay on their electricity, through the Ministry of Industry's annual calls. Rigorous metering and energy reporting make the file easier to prepare and defend.

Data: Red Eléctrica, OMIE, MITECO, Ministry of Industry and public announcements. Models, tables and analysis: Solar-Tec. Models are illustrative and do not replace the sizing of a specific site.

Start a conversation

Want to know how much headroom your connection has?

Tell us about your consumption, contracted power and growth plans. We will tell you what is worth measuring and which study makes sense.